Building Permits in Saudi Arabia: A Practical Guide to the Balady Process and Engineering Approvals

Building Permits in Saudi Arabia: A Practical Guide to the Balady Process and Engineering Approvals

For many owners, the building permit is the first real test of a project. Land has been bought, a concept has been sketched, financing is lined up, and nothing can start on site until the permit is issued. The good news is that the process has changed substantially: building permits in Saudi Arabia are now applied for and issued electronically through the Balady platform of the Ministry of Municipalities and Housing. The less obvious news is that speed still depends on preparation. A complete, coordinated submission moves quickly; an incomplete one goes back and forth.

This guide explains how the process works, what documents are needed, and where delays usually come from.

Who does what in a Balady building permit

The permit is the owner's, but the technical submission is prepared by a licensed engineering office. According to Balady's service description, the process runs broadly as follows:

  • The owner, or an authorised representative, logs in to Balady and authorises a design engineering office to start the building permit application.
  • The design office accepts the delegation through its business account, selects the land's survey decision, and prepares and uploads the architectural and structural designs, together with other drawings the building category requires.
  • The supervising engineering office and the construction contractor are designated.
  • Once the application has been reviewed and fees are paid, the permit is issued electronically and can be printed.

Balady lists a service duration of between one and ten days for issuing a building permit. That figure describes the platform's processing time; the time it takes to prepare a complete, compliant design comes before it.

Documents and prerequisites

The requirements published on Balady for a building permit include:

  • An updated electronic title deed from the Ministry of Justice, or a housing or investment contract.
  • A valid survey (cadastral) report for construction purposes.
  • A contract with an engineering office for the architectural designs.
  • A contract with a supervising engineering office and a construction contractor.
  • Latent defects insurance for the building, where the building type requires it.
  • A soil study report.

Some activities also require a traffic study. For applications submitted after 25 June 2025, Balady states that insurance documents are issued within the beneficiary's journey on the platform itself.

Two of these items often cause avoidable delays. The first is the survey decision: if boundaries, areas or coordinates on the title deed do not match the land, the discrepancy must be resolved before design can be finalised. Aknan's surveying services team handles boundary determination, survey decisions and deed-related updates for exactly this reason. The second is the soil report, which should be commissioned early because foundation design depends on it.

What the engineering office is really responsible for

The engineering office does more than upload drawings. It prepares a design that complies with the Saudi Building Code and local planning regulations, including permitted uses, setbacks, heights, parking and any architectural guidelines that apply to the area. It certifies compliance and takes professional responsibility for the design. Fee levels, Balady notes, are a matter of agreement between the office and the client.

This is why the choice of office matters. Drawings that are internally inconsistent, that misread the zoning regulations, or that do not resolve structural and MEP requirements are the most common reasons for returned applications.

Beyond new buildings: renovations, demolition and existing structures

Not every permit is for a new building on vacant land. Owners frequently need to:

  • Obtain renovation or modification permits for changes to existing buildings.
  • Renew, amend or revise an existing building permit, for example when a design changes during construction.
  • Apply for demolition permits.
  • Regularise existing structures that were built without a permit or that differ from their approved drawings.

The last category is often the most complex. Where records are incomplete or site conditions do not match approved drawings, authorities may require technical reports to clarify the building's actual condition, sometimes described as reports for the removal of ambiguity. In these situations, a formal engineering judgment prepared and stamped by a licensed engineer can support the application, provided the authority formally accepts it.

Approvals beyond the municipality

Depending on the building's use and size, other approvals can be needed alongside the municipal permit, including no-objection certificates from service providers and, for many non-residential buildings, fire and life safety review by Civil Defense. Coordinating these in parallel, rather than in sequence, is one of the simplest ways to shorten the overall timeline.

How to avoid the most common delays

  • Verify the title deed and survey decision before design starts, and fix discrepancies first.
  • Commission the soil investigation early so structural design is not held up.
  • Confirm zoning, setback, height and parking requirements for the plot at concept stage.
  • Make sure architectural, structural and MEP drawings are coordinated with each other before submission.
  • Appoint the supervising office and contractor early enough that the permit is not waiting for them.

Fitting the permit into the project timeline

Owners often plan around the platform's processing time and forget the work that comes before it. In practice, the critical path to a permit usually runs through land records, the soil investigation and design development, not the review itself. A realistic programme allows time to resolve any title or survey discrepancies, to complete geotechnical fieldwork and reporting, to develop a coordinated design across disciplines, and to respond to any comments raised during review. Appointing the design office, supervising office and contractor in good time, and agreeing their scopes clearly, keeps the application moving once it is submitted.

After the permit

The permit is the start of the regulatory journey, not the end. Construction must follow the approved drawings, changes must be approved, and the supervising office documents progress through construction. At completion, a certificate confirming that the building was constructed in accordance with the permit is typically required before occupancy and utility connections.

Conclusion

Electronic permitting has made the building permit process in Saudi Arabia faster and more transparent, but it has not removed the need for careful preparation. Clean land records, an early soil study, a code-compliant and coordinated design, and early appointment of the supervising office will do more to speed up approval than anything else.